Move guide

Run the programme

Your report suggested a move on at least one of these four practices:

  • whether a central team runs the programme and owns one set of numbers;
  • how progress is reviewed;
  • whether benefits are tracked with lead and lag measures;
  • what happens when an initiative goes red.

This move guide sets up a small central team with one tracker. Weekly reviews look forward, and benefits are tracked against forecast every month. A red initiative is worked inside a week.

1. When it applies

Use this move guide if your report placed any of these four practices in the lowest two stages.

Practice Where it may sit today Where this move guide aims
Whether a central team runs the programme and owns one set of numbers Lagging: "There is no central team, every workstream reports its own way, and status lives in slide decks."
Basic: "A programme office exists, but it either chases templates for the steering pack or does the initiatives' work itself, so everything waits on it."
Competent: "A small central team, led by someone who does nothing else, keeps the one tracker that every initiative's status and benefits sit in."
How progress is reviewed Lagging: "Progress is reviewed from backward-looking slides whenever someone calls a meeting, amber means someone was on leave, and decisions slip to the next one."
Basic: "Reviews happen on a calendar but are status readouts; problems are noted and nothing is decided in the room."
Competent: "Weekly workstream reviews ask what is late, broken or coming up next, and a monthly executive review makes decisions and records them."
Whether benefits are tracked with lead and lag measures Lagging: "Benefits are asserted at the end of the year, and the answer to 'how do we know' is 'we'll see it in the results'."
Basic: "Dollars are tracked by initiative on a spreadsheet updated when someone remembers, and there are no early-warning measures."
Competent: "Forecast and actual benefits are tracked monthly by initiative against a hard baseline, and each initiative has one activity or adoption measure that moves before the dollars do."
What happens when an initiative goes red Lagging: "A red initiative stays red for months, and the owner is blamed for it."
Basic: "A red initiative gets a slide and a new date."
Competent: "Within a week someone from the centre or the top team works the problem with the owner, and the decision (fix, resize, stop) is recorded."

If all four already sit at the middle stage or higher, skip this move guide.

It runs from launch to the end of the programme, on the waves from sequencing the waves and banking early wins.

2. What to do

Five steps. Set them up at launch, then run them every week and every month.

  1. Stand up a small central team of the business's own people, led by someone who does nothing else. It keeps one tracker for every initiative. The transformation-office worksheet sets it up.
  2. Run weekly reviews that look forward. Ask what is late, what is blocked and who clears it. Hold a monthly executive review that makes decisions and records them. The review-cadence worksheet holds the agenda.
  3. Track each initiative's benefit against forecast every month, against a hard baseline. Give each one a lead measure that moves before the money does. The benefits-tracking worksheet does this.
  4. Work a red initiative inside a week. Someone from the centre or the top team works it with the owner. Decide to fix it, resize it or stop it, and record the decision. The troubleshooting worksheet holds the routine.
  5. Move each initiative through gates, as in the chart below. Each gate has its own sign-off.
Gates from idea to close

Stages

  1. Idea
    • Name the improvement
    • Estimate the benefit
  2. Business case
    • Cost and benefit
    • Options and risks
    • A plan to deliver
  3. Detailed plan
    • Scope, timing and measures
    • Roles, resources and risks
  4. Delivery
    • Deliver against targets
    • Report progress regularly
  5. Close
    • Final report
    • Benefits in the budget

Sign-off at each gate

  • Idea to business case: Approval to analyse it further
  • Business case to plan: The programme board approves the case
  • Plan to delivery: The programme board approves the plan
  • Delivery to close: The programme board signs off the close

Table A below holds one tracker line per initiative.

The four free worksheets do the recording:

3. What to produce

One table, plus the four worksheets above.

Table A. The tracker

Initiative Gate Status Benefit forecast ($) Benefit actual ($) Lead measure, reading now If red: decision and date

A red line with no decision beside it is a problem nobody owns.

4. A worked example

Illustrative. Written for this move guide. It describes no client.

A hospital group's programme reports through four workstream decks, each in its own format. Amber usually means someone was away.

The office.

  • A finance manager now leads a team of three, full time, with one tracker. Every initiative's status and benefit sits in it.

The reviews.

  • Workstream reviews run every Monday and ask what is late or blocked. The monthly executive review records each decision in the tracker.

The benefits.

  • Each initiative now has a lead measure. Theatre scheduling, for example, tracks the share of sessions booked a week ahead.

The red initiative.

  • Procurement savings went red in the second month. Within a week, the chief financial officer and the owner resized it and set a new measure.

Two months on.

Two months on Illustrative
  • 1 tracker, kept by a full-time team of three
  • All initiatives with a lead measure
  • 1 week from red to a recorded decision

On a retake, all four practices could be answered at the middle stage.

What it looked like in our work

From our own work. Redrawn.

An equipment maker's programme office reported each month on every initiative: its due date, its status and a line of comment. Beside it sat the benefits to date, against forecast.

Initiative Status Comment
Set up the programme office Complete Office running, and status reporting started
Overheads: research Complete
Overheads: sales and marketing Complete
Overheads: administration On track Most of the agreed reductions made
Overheads: manufacturing On track
Sale of a business line On track Interest from more than one party
Product range Delayed Key sales staff were not free to check the opportunity
Sales force effectiveness On track Needs clear baseline measures and tracking
Growth plan for a product line Not started Starts later in the year
The monthly benefits page Redrawn
  • Each month benefits to date against the forecast
  • 3 causes for each month's variance: the programme, the underlying business, and other effects such as currency

The delayed line named its cause. The variance split showed which gaps belonged to the programme.

5. Effort and dependencies

Who
  • Programme office leadRuns the central team and keeps the tracker.
  • Programme ownerChairs the monthly review and takes the red initiatives.
  • Initiative managersReport weekly, with the lead measure.

What you need

How long

  • From launch to the end of the programme: weekly and monthly.

What gets in the way. We have seen these in our own work:

  • Advisers as the office. An equipment maker's programme office was its adviser, about a day a week. The business owned the benefits, but not the office.
  • What good looked like. The same business's monthly update showed benefits forecast against actual, and each leak named by initiative and cause.

6. How will you know it worked?

The test is the tracker and the decisions recorded in it. Retake the check after the third monthly review. Each of these should be true when you answer:

Practice You can answer Competent when A document alone does not count if
Whether a central team runs the programme and owns one set of numbers A small team, led by someone who does nothing else, keeps one tracker. The tracker exists, but workstreams still report their own way.
How progress is reviewed Weekly reviews look forward, and a monthly review makes and records decisions. The reviews run, but they only read out status.
Whether benefits are tracked with lead and lag measures Benefits are tracked monthly against a baseline, and each initiative has a lead measure. The dollars are tracked, but nothing moves before them.
What happens when an initiative goes red A red initiative is worked within a week, and the decision is recorded. Red initiatives get a new date and nothing else.

The worked example is illustrative.

Start the check