Worksheet · Transformation Readiness Check

Work a red initiative inside a week

It prints on A4 with room to write.

A red initiative that only gets a slide and a new date stays red. This sheet sets who works the problem, by when, and what gets decided. It builds the Competent step of the check:

Within a week someone from the centre or the top team works the problem with the owner, and the decision (fix, resize, stop) is recorded.

Step 1. The rule

Item Your rule
What makes an initiative red e.g. Forecast benefit more than 20% below plan, or a check point missed by two weeks
Who is sent to help
Within how many days 7
Who records the decision

Step 2. The working session

Take these questions into the first meeting with the owner.

  1. What is behind: the pace of rollout, the execution, or the target itself?
  2. What would it take to fix, and who has that skill or time?
  3. Is the benefit still worth the effort at a smaller size?
  4. If we stop it, what replaces its value?

Step 3. The red log

Initiative Went red on Why (late, smaller, broken) Helper Met on Decision (fix, resize, stop) New date or value Recorded by

Treat a red as a problem to solve. Blame teaches owners to hide the next one.

Under 50 people: the owner or a senior manager works the problem with the initiative's lead inside a week. Record what comes out of it: fix, resize or stop.

Done when: every initiative that went red last quarter had help within a week and a recorded decision.


Adapted from our own benefits-tracking training (PSP, 2013).

From the Transformation Readiness Check. Your report links the sheet for each of its moves.