Move guide

Find, define and value the initiatives

Your report suggested a move on at least one of these two practices:

  • how well each initiative is defined;
  • whether the benefits add up.

This move guide finds the initiatives by asking four questions of every activity. It gives each initiative a one-page brief. Then it tests each benefit before it counts, so the total adds up once.

1. When it applies

Use this move guide if your report placed either practice in the lowest two stages.

Practice Where it may sit today Where this move guide aims
How well each initiative is defined Lagging: "There is a long list of ideas at every stage from hunch to half-done, and nobody can say who owns most of them."
Basic: "Initiatives have a name, an owner and a round-number benefit; scope, baseline and milestones are still to come."
Competent: "Each initiative has a one-page brief with owner, scope, baseline, value, milestones and measures."
Whether the benefits add up Lagging: "Savings are claimed with no baseline, two workstreams count the same saving, and cuts made before the programme are booked to it."
Basic: "A baseline exists, but the benefits total is a sum of initiative estimates that nobody has checked for overlap."
Competent: "Finance signs off each benefit against a hard baseline before it counts, and the one-off cost to achieve is in the budget beside them."

If both already sit at the middle stage or higher, skip this move guide.

It fills the workstreams from shaping the programme and giving it owners with defined, valued initiatives.

2. What to do

Five steps, in four to eight weeks, in waves.

  1. Ask four questions of each activity. Can we stop it or do less? Can we cut its overhead? Can someone else do it? Can we do it more efficiently? The tree below lists the fifteen levers those questions lead to.
  2. For each unit, set out why it exists and what it does. Then list what each activity produces, what it costs and the value it adds.
  3. Give every initiative a one-page brief. Owner, scope, baseline, benefit, cost to achieve, milestones and measures. The initiative-definition worksheet holds the briefs.
  4. Test each benefit before it is counted. It must tie to a line of the profit and loss. It must be counted once. It must be something that would not have happened anyway. The value-logic worksheet runs the test.
  5. Weigh each initiative's saving against its risk. Low risk is a go. A low saving with any real risk is a no-go, as the grid below shows.
Fifteen levers to take cost out
  • Take cost out
    • Reduce the services
      • Eliminate
      • Reduce the quality
      • Reduce the scope
      • Reduce the frequency
      • Allow a longer response time
      • Reduce the demand from inside
    • Improve efficiency
      • Make the organisation leaner
        • Centralise or decentralise
        • Fewer layers, wider spans
        • Move it to another unit
        • Outsource
        • Move it offshore
      • Make the work more efficient
        • Streamline
        • Standardise
        • Automate
        • Change the skill level

The first six answer "can we stop it or do less?". The rest cut overhead, use others, or make the work itself more efficient.

Go, maybe or no-go
Expected saving: Low to High. Risk: Low to High
High saving, Low risk: GoHigh saving, Medium risk: MaybeHigh saving, High risk: Maybe
Medium saving, Low risk: GoMedium saving, Medium risk: MaybeMedium saving, High risk: No-go
Low saving, Low risk: GoLow saving, Medium risk: No-goLow saving, High risk: No-go

Weigh the expected saving against the risk of cutting the activity.

Risk here is how likely a bad consequence is, and how serious it would be.

The two free worksheets do the recording:

3. What to produce

One table, plus the two worksheets above.

Table A. The initiatives, valued once

Initiative Owner (name) Lever Baseline ($) Benefit ($) Cost to achieve ($) Signed off by finance
Total

A benefit finance has not signed off does not count yet.

4. A worked example

Illustrative. Written for this move guide. It describes no client.

A software and services business has a list of 60 ideas. Most have a name and a round-number benefit. Two workstreams both claim the same office move.

The briefs.

  • The programme office cut the list to 22 initiatives, each with a one-page brief. The rest were merged or dropped.

The benefits.

  • Finance tested each benefit against last year's actual costs. The office move now counts once. A hiring freeze from before the programme came out of the total.

The cost to achieve.

  • Each brief carries its one-off cost, and the total sits in the budget beside the benefits.

Six weeks on.

Six weeks on Illustrative
  • 22 initiatives, each with a one-page brief
  • All benefits signed off against a baseline
  • 1 saving that had been counted twice, now counted once

On a retake, both practices could be answered at the middle stage.

What it looked like in our work

From our own work. Figures changed.

An equipment maker listed each initiative with its potential benefit. Beside it sat the amount already in the coming year's budget. Most of the list was new money the budget did not yet hold.

Potential benefit by initiative, and the part already in the budget Figures changed
  • Potential benefit ($m)
  • Already in the budget ($m)
Potential benefit by initiative, and the part already in the budget
Potential benefit ($m)Already in the budget ($m)
Fixed overheads4.43.4
Recovery of a cyclical product line2.20
Product range1.80
Plants1.41.2
Business portfolio1.20
Sales force0.80

Each bar is the initiative's potential benefit. Each marker is the amount already in the budget. Values in millions of dollars.

Initiative Potential benefit ($m) Already in the budget ($m)
Fixed overheads 4.4 3.4
Recovery of a cyclical product line 2.2 0
Product range 1.8 0
Plants 1.4 1.2
Business portfolio 1.2 0
Sales force 0.8 0
Brand consolidation 0 0
Trade terms 0 0
Total 11.8 4.6

Less than half the list was already in the budget. Two more initiatives, in the table but not the chart, carried no saving yet. One was there for focus, and one needed a review before anyone could size it.

5. Effort and dependencies

Who
  • Programme officeRuns the four questions with each unit and keeps the briefs.
  • Workstream leadsOwn the initiatives in their workstream.
  • FinanceSigns off each benefit against the baseline.

What you need

  • The cost base by unit and activity.
  • Last year's actual costs, as the baseline.

How long

  • Four to eight weeks, in waves.

What gets in the way. We have seen this in our own work:

  • Opportunities nobody defined. A drinks producer's audit found poorly defined opportunities and no plan for realising the benefits.

6. How will you know it worked?

The test is the briefs and finance's sign-off. Retake the check once every initiative has a brief and the total is signed off. Each of these should be true when you answer:

Practice You can answer Competent when A document alone does not count if
How well each initiative is defined Each initiative has a one-page brief with owner, scope, baseline, value, milestones and measures. The briefs exist, but half the boxes say "to come".
Whether the benefits add up Finance has signed off each benefit against a baseline, and the cost to achieve is in the budget. The total is a sum of estimates nobody has checked.

The worked example is illustrative.

Start the check