Worksheet · Strategy Health Check

Give every theme an action programme

It prints on A4 with room to write.

A strategy that never reaches team plans stays a document. This sheet turns each theme into initiatives with owners, dates and a deliverable for this quarter. It builds the Competent step of the check:

Strategic priorities appear in team plans and goals with dates and owners.

Step 1. One table per theme

Theme: ________ Sponsor: ________

Initiative Lead This quarter's deliverable Milestones, next 12 months Team plans it appears in Cost Status
e.g. Cross-functional key-account teams Sales director Teams named for the top ten accounts Joint plans agreed with five accounts by June Sales; supply chain; finance Staff time On track

Step 2. Push it into team plans

For each initiative, check the plans of the teams that must deliver it.

Team Initiative Appears in the team plan? Appears in someone's personal goals? Date checked

Step 3. Review it monthly

Thirty minutes, the same table each month, three questions:

  1. Was this quarter's deliverable met, or when will it be?
  2. What is blocking the next milestone?
  3. Does any initiative need more people, fewer, or to stop?

Done when: each priority appears in the named teams' plans and goals with a date and an owner, and the table is reviewed every month.


Adapted from our own strategy templates (PSP, 2011).