Worksheet · Transformation Readiness Check

Put the programme in the CEO's diary

It prints on A4 with room to write.

A programme the CEO attends when the diary allows is a side project. This sheet fixes the CEO's time and the reporting rhythm up to the board. It builds the Competent step of the check:

The CEO chairs the programme reviews personally and the board or owners hear progress every quarter.

Step 1. The rhythm

Forum How often Chair Who attends What it decides First date
Programme review Weekly CEO Workstream leaders, programme lead What is late or blocked, and who clears it
Leadership team slot Monthly CEO Leadership team One workstream in depth; benefits against plan
Board or owners Quarterly CEO presents Board or owners Progress, benefits, risks, asks

Put every date for the next twelve months in the diary now.

Step 2. The CEO's week

Slot Day and time Moved only for Kept this week?
e.g. Programme review Monday 8.00 to 9.00 A safety incident
Programme review
Time to clear obstacles between reviews

Step 3. The first board report, inside ninety days

Section What goes in it Ready?
Target and progress Benefits planned and delivered to date
Workstreams Status of each, with its leader
Risks The three that matter, each with an owner
Asks Decisions or support the board is asked for

Month-to-month swings in benefits can mislead a board. Report the cumulative figure against plan.

Under 50 people: the owner or CEO chairs the weekly review in person. Report progress each quarter to the other owners, or to the board if there is one.

Done when: the CEO has chaired the weekly review in person, and the board or owners have had a progress report in the last quarter.


Adapted from our own programme steering packs (PSP, 2013).